Seven stages, published in advance.
No black boxes.

Every MNG project follows the same documented methodology. You know the duration, the deliverables, and the QA gate of every stage — before we break ground.

  1. 01

    Planning & Feasibility

    4–8 weeks

    Land due-diligence, soil investigation, FSI analysis, and financial modelling before a single line is drawn.

    Deliverables

    • Feasibility report
    • Soil & survey data
    • Budget envelope
    • Regulatory map
  2. 02

    Architectural Design

    10–16 weeks

    Concept to construction drawings with structural, MEP, and facade consultants working as one integrated team.

    Deliverables

    • Concept design
    • GFC drawings
    • BIM model
    • Material specification
  3. 03

    Approvals & Permits

    6–12 weeks

    RERA registration, plan sanction, environmental and fire NOCs — managed end-to-end by our liaison team.

    Deliverables

    • Sanctioned plans
    • RERA registration
    • Environmental clearance
    • Commencement certificate
  4. 04

    Excavation & Foundation

    8–20 weeks

    Shoring, dewatering, piling, and raft foundations — executed with third-party verification at every pour.

    Deliverables

    • Pile load tests
    • Foundation QA records
    • Waterproofing certificates
    • As-built survey
  5. 05

    Superstructure

    Floor cycle: 7–10 days

    Aluminium formwork systems and disciplined floor cycles that keep towers rising on a published schedule.

    Deliverables

    • Cube test registers
    • Cycle-time reports
    • Alignment surveys
    • Rebar inspection logs
  6. 06

    MEP & Finishing

    Parallel · 24 weeks

    Services and finishes run in parallel with structure — pressure-tested, megger-tested, and mock-up approved.

    Deliverables

    • Pressure test records
    • Mock-up sign-offs
    • Finish schedules
    • Snag registers
  7. 07

    Quality, Handover & Aftercare

    4–8 weeks + 60-month warranty

    A 240-point QA checklist per unit, documented handover, and a structural warranty that runs for five years.

    Deliverables

    • QA clearance
    • Handover dossier
    • O&M manuals
    • 60-month warranty card